Project Huckleberry

SRP supports long-term economic development in the communities it serves by providing reliable power to its customers.

About the project

On Aug. 16, 2022, the Arizona Corporation Commission (ACC) voted unanimously to approve a Certificate of Environmental Compatibility (CEC) for Project Huckleberry. This project will allow SRP to construct a half-mile 230 kilovolt (kV) transmission line and 230 kV substation to provide energy to a new data center for Meta located in Mesa, Arizona.

SRP received a request to provide energy to a new data center for Meta located in Mesa, Arizona. This project will require SRP to build an approximately half-mile 230 kV transmission line and substation to serve the data center located at the southeast corner of Elliot and Ellsworth roads. The data center continues the Phoenix area’s growth in the technology sector and is expected to support 200 high-wage jobs upon its completion and around 2,000 jobs during its construction. SRP supports long-term economic development in the communities it serves by providing reliable power to its customers.

We have notified customers, property owners and stakeholders about the proposed project.

SRP prepared an application seeking a Certificate of Environmental Compatibility (CEC) and filed it with the Arizona Corporation Commission (ACC). The CEC process included public hearings with the Arizona Power Plant and Transmission Line Siting Committee before seeking final approval from the ACC.

This project is now online.

Why is this project needed?

On Aug. 12, 2021, Meta announced a development plan for its Mesa Data Center in Mesa, Arizona. The data center site is located on a 389-acre parcel of land at the southeast corner of Elliot and Ellsworth roads.

The Mesa Data Center is expected to create approximately 200 permanent high-tech, high-wage jobs and approximately 2,000 jobs during its construction. The development represents a continuation of technology sector growth in Arizona, especially data center growth for which the Phoenix area recently ranked second nationally.

SRP supports long-term economic development in the communities it serves by providing reliable power to its customers. The Mesa Data Center and other industrial customers in the area require SRP to provide reliable power to support their ongoing growth. SRP serves the electrical load in the area using a network of 69kV lines connect to three nearby 230kV stations located in the City of Mesa and the Town of Gilbert. Connecting the Mesa Data Center directly to SRP's 230kV system meets the customer's reliability needs while balancing demand across SRP's remaining 69kV network.

To meet the customer's December 2022 in-service date, SRP will serve the Mesa Data Center from the 69 kV system and build the new Prickly Pear 69 kV Switchyard. To meet the ultimate reliability and power quality requirements from Meta, Project Huckleberry will connect the data center to SRP's 230 kV transmission system. With the Prickly Pear 69 kV Switchyard in place, SRP intends to construct two 230 kV transmission circuits for the Mesa Data Center by April 2024. By utilizing the existing 69kV infrastructure to meet Meta's initial schedule request, the quantity of new required 230kV transmission circuits is reduced from three to two. As the primary beneficiary of Project Huckleberry, Meta is funding the cost of SRP's electrical infrastructure required to serve the Mesa Data Center.

Construction timeline

  • Prickly Pear Substation and 230 kV Transmission Line Construction: February 2023
  • Prickly Pear Substation and 230 kV Transmission Line In-Service: May 2024

Project maps

Project Study Area

Below is a map showing the Project Huckleberry components for which SRP received a Certificate of Environmental Compatibility (CEC) approval for. Note that this is the total study area, which includes existing and planned construction for SRP infrastructure as well as customer owned facilities which was not included in the CEC application.

Project Details Map #1

The map below indicates (in green) the roughly half-mile transmission line and Substation that SRP received CEC approval.

Project Details Map #2

This map provides the same details (in green) of only the components that SRP received CEC approval for, but overlayed on a satellite based aerial image.

Transmission line structure types

Below are the transmission structure types that will be used for the project.

How electricity gets to you

Frequently asked questions

News archive

See the latest project news and announcements below.

June 13, 2022
Hearings for SRP Application for Transmission Line and Substation to Serve Meta Data Center
Salt River Project submitted an application for a Certificate of Environmental Compatibility (CEC) with the Arizona Corporation Commission (ACC) for "Project Huckleberry." The ACC's Power Plant and Transmission Line Siting Committee will consider the application at a public hearing beginning on June 27, 2022, at 1 p.m. at the Delta Hotels by Marriott Phoenix Mesa at 200 N. Centennial Way, Mesa, AZ, 85201.

Read more

March 4, 2022
SRP Announces Proposed Mesa-Based Half-mile Transmission Line and Substation to Serve Meta Data Center
SRP today announced a proposed half-mile 230 kV transmission line and substation to serve energy to a data center being built for Meta (formerly Facebook), located in Mesa, and slated to be fully operational by 2024.