disponible únicamente en inglés

Project Red Hawk CEC filing

On Sept. 23, 2019, SRP filed an application for a Certificate of Environmental Compatibility (CEC) with the Arizona Corporation Commission (ACC).

All documents filed with the ACC related to Project Red Hawk are available on the ACC eDocket websiteOpen new site..


On this page:

    CEC approval

    Project Red Hawk was heard before the Arizona Power Plant and Line Siting Committee and received a recommendation to approve the CEC on a 7-1 vote. The switchyard has been required to be constructed with the area SRP had defined and proposed at the northern portion of the project site; however, the switchyard will be constructed as far south as practical within the designated location. The Committee required a 10 foot wall be constructed on the North and East side of the switchyard to mitigate the visual impact of the switchyard.

    On Dec. 10, 2019, the ACC unanimously approved the CEC for the project. The approval is the final step of the application process and enables SRP to move forward with project design and construction. ACC Decision No. 77551: CEC ApprovalDocument is a PDF

    Transcripts

    Download the CEC

    1. IntroductionDocument is a PDF
    2. CEC applicationDocument is a PDF
    3. Exhibit A: Project Location and Land UseDocument is a PDF
    4. Exhibit B: Environmental StudiesDocument is a PDF
    5. Exhibit C: Areas of Biological WealthDocument is a PDF
    6. Exhibit D: Biological ResourcesDocument is a PDF
    7. Exhibit E: Scenic Areas, Historic Sites and Structures, Archaeological SitesDocument is a PDF
    8. Exhibit F: Recreational Purposes and AspectsDocument is a PDF
    9. Exhibit G: Concepts of Typical FacilitiesDocument is a PDF
    10. Exhibit H: Existing PlansDocument is a PDF
    11. Exhibit I: Noise Emissions and Communication InterferenceDocument is a PDF
    12. Exhibit J: Special FactorsDocument is a PDF

    Additional documents filed with the ACC relating to SRP's application